Cripps Court - on site

Selwyn College, Cambridge | April 2014

With the first two phases completed on time, the third and final phase has now started on site. Currently on programme for an anticipated completion date of early September 2014 the scaffolding and temporary roof are up so construction of the additional fourth floor and restoration of the existing flint and stone cladding can commence. Internally, electrical first fix and partitioning are well advanced with insulated lining to the external envelope and mechanical first fix about to start.  The new build gym is also underway.
As well as fulfilling our general role producing construction information for the main contactor we have recently been working closing with a local metal fabricator, fine tuning the details to a new entrance gate for the Court.   