UoB | New Library - on site

Luton | June 2014

Following the fulfilment of our role as part of the design team on this exciting new build scheme for the University of Bedfordshire delivering a Stage E+ design on a compressed programme, we saw the scheme through the tender process to the appointment of a main contractor in December 2013.
Since then we have been novated over to the construction team and are currently in the process of producing construction information and coordinating our design with both civil and structural engineers and the recently appointed M&E sub-contractors. Work has commenced on site with piling in progress and party wall matters being resolved. Archaeologists are also keeping a watching brief as the ground works continue.